TEL TSI - Deadlines and compliance
Go back to the main TEL TSI FAQs page.
By the Appendix G milestones for each function, between 14 December 2025 and 9 December 2029. Operators of rail freight service facilities have 12 more months. See the Deadlines page for the full calendar.
Any telematics application deployed after 2 March 2026 must comply with the TEL TSI from the start (Article 16(1)).
Yes, by up to 12 months, where a project planned or implemented under the former TAF or TAP TSI has reached a point where complying with the TEL TSI would compromise putting it into service (Article 16(5)).
By self-assessing your messages in the Agency web application, applicable from 2 March 2027. You upload the serialised messages and the XSD or SHACL files used to validate them. A positive result gives an evidence-based declaration and a presumption of compliance for the messages tested and the application that uses them, and your application is listed as presumed compliant.
No. Compliance is self-assessed. The Agency checks the correctness of a self-assessment when there is a justified doubt, at the request of the Commission or another body, or for projects applying for EU funding. Positive assessments issued before 2 March 2026 remain valid unless the application changes.
Until compliance is proven, you report your implementation status and plans through the Agency web application: infrastructure managers by 2 September 2027; freight RUs, operators of rail freight service facilities, station managers and passenger RUs by 2 March 2028.